Project Diary
|
Top Previous Next |
| If you print out the Daily Job Sheet and have your foreman fill them in each day, then you can use them to help you fill in the information.
|
| You must first select the project this diary entry belongs to from the Project drop-down list. Once you select a project the current date will be entered in the Date field. You can change it as needed. Also if you had selected a foreman for the project on the Projects screen, then that foreman will be selected in the Foreman field. A default subject will also be entered in the Subject field for you. Edit this as required. This all helps to speed up entries and save typing.
|
| You can enter the weather conditions in the Weather field and add notes in the Notes field.
|
| Check the Automatically Update Job Tracking Info box if you want the actual quantities updated in the Job Tracking each time you add an entry for a project. This can save a lot of work plus it makes it easier to track the progress of the job.
|
| To add activity details for the day first select the category (Materials, Labor, Subcontract, Equipment & Miscellaneous). Then select an item from the Item drop-down list. Only items that were included in the estimate will be available from the list. If the item you want is not on the list, you can click the |
| Next enter the quantity used/installed for that day in the Today's Quantity field. The Unit field will already be filled in for you.
|
| When you click on the Labor category to enter labor items, a small |
|
|
|
| Simply select an employee from the Employee drop-down list. Then enter the hours the worked on that task. If you have entered the hourly rate for your employees on the Employees screen, then the cost will be calculated for you. Repeat for each employee who worked on the task.
|
|
|
| The Cost Per Man-Hour, Total Man-Hours and Total Cost will be shown at the bottom of the screen. Click the Close button to return to the Project Diary screen. The Total Man-Hours will be entered into the Today's Quantity field for you.
|
|
|
| You can print a report named Detailed Blank Daily Time Sheet from the Estimate Print Options screen. This report will list all the labor item from the estimate with room to add up to four employees and their hours for each item. Use this screen on site to collect the required information to fill in the Project Diary Labor Task Details form.
|
|
|